Enbridge’s contentious plan to reroute an aging pipeline around a northern Wisconsin tribal reservation moved closer to reality Thursday after the company won its first permits from state regulators.
Wisconsin Department of Natural Resources officials announced they have issued construction permits for the Line 5 reroute around the Bad River Band of Lake Superior Chippewa’s reservation. The energy company still needs discharge permits from the DNR as well as the U.S. Army Corps of Engineers.
The project has generated fierce opposition. The tribe wants the pipeline off its land, but tribal members and environmentalists maintain rerouting construction will damage the region’s watershed and perpetuate the use of fossil fuels.
The DNR issued the construction permits with more than 200 conditions attached. The company must complete the project by Nov. 14, 2027, hire DNR-approved environmental monitors and allow DNR employees to access the site during reasonable hours.
Story continues below advertisement
The company also must notify the agency …